HV & EHV grids - Project examples
-
Rwanda, Burundi - Regional Interconnection Project (220 kV Transmission Line Kigoma - Butare - Ngozi - Gitega and 220/110 kV Substations)
The project was part of the NELSAP Regional Transmission Program that aimed at interconnecting five of the Nile Equatorial Lakes Countries, i.e. Burundi, DR Congo, Kenya, Rwanda and Uganda.
The project interconnected the electricity networks of Burundi and Rwanda through the construction of a new 220 kV single-circuit transmission line with a total length of 143 km. The line will initially be operated on the 110 kV level and might later be upgraded to 220 kV.
The project also included the construction of two new 220/110 kV substations, the extension of two existing 110 kV substations and the construction of 11.2 km of 30 kV line for rural electrification of Gisagara (Rwanda).
intec's services
- Review of existing feasibility studies
- Update of the Environmental and Social Management Plan (ESMP)
- Detailed design
- Preparation of complete tender documents for EPC Contractors (2 lots)
- Technical assistance during the procurement process, i.e. tendering, bid evaluation and contract award
- Preparation of a detailed Resettlement Action Plan (RAP) and monitoring of its implementation
- Design approval and supervision of implementation works
- Witnessing of factory acceptance tests, supervision of testing and commissioning
- Certification of Contractor's invoices and payments
- Monitoring and supervision of the implementation of the ESMP
- Safeguarding of project's compliance with KfW's and the World Bank's sustainability guidelines
- Technology transfer and training of employers' and project executing agency's staff
- Representation in the respective project steering and technical committees
Client
REGIDESO (Burundi), Energy Development Corporation Ltd. (Rwanda)Financing
KfW EntwicklungsbankPeriod of implementation
03.2015 - 06.2017 -
Congo (RD) - Revision of the Studies on the 220 kV Line Kamanyola - Buhandahanda
The 220 kV Kamanyola - Buhandahanda line shall evacuate the electricity generated by the Ruzizi III Hydropower Plant which is part of the 220 kV interconnected network of the CEPGL (Communauté Economique des Pays des Grands Lacs - Economic Community of the Great Lake Countries). Studies for this line were finalised in September 2011 and shall be revised under the present project with the aim to take into consideration the new locations of the Kamanyola and Buhandahanda Substations and the new line concept.
intec's services
- Review of the project's technical feasibility, in particular through revision of the line's general concept (review of the line route and harmonisation of the design (double-circuit line with possibly only one single circuit operated in the first phase), study of the grid stability with the new line, set-up of a simulation model of the interconnected network, power distribution and load flow studies, review of the line protection system)
- Review of the project's economic and financial feasibility (cost estimates, economic and financial viability, proposals for project financing and implementation)
- Preparation of the detailed design for the revised line concept, elaboration of the longitudinal profile on the basis of satellite data, and tower spotting
- Preparation of an Environmental and Social Impact Assessment (ESIA) and an Environmental Management Plan (EMP) in conformity with international standards, and elaboration of a Resettlement Action Plan (RAP)
- Elaboration of the tender dossier
- Organisation of a validation seminar with EGL, SNEL (National Power Company of Congo), the Steering Committee and KfW
- Participation in the project appraisal mission.
Client
Energie des Grands Lacs - EGLFinancing
KfW EntwicklungsbankPeriod of implementation
07.2015 - 03.2017 -
Uganda - Interconnection Code & Wheeling Agreement
The preparation of an interconnection code and a wheeling agreement is part of the GET FiT Uganda Program, launched in May 2013 to promote private investment into renewable energy generation projects in Uganda.
The main purpose of program is to fast-track a portfolio of about 20-25 small-scale renewable energy generation projects (promoted by private developers with a total installed capacity of roughly 150 MW). The overall objective of the present assignment is to enable proper and full evacuation of embedded generators in the future, at allowable national and international techno-economic standards.
The project includes detailed technical and economic requirements for connecting generation facilities to the existing grid and will involve both interconnection and wheeling aspects.
For this purpose, the following work packages constitute the framework of the project:
Part A - Work Package 1: Interconnection and Grid Code for fluctuating renewable energy power integration into the grid
Part B - Work Package 2: Wheeling Agreement for fluctuating renewable energy power wheeling
Part C - Work Package 3: Knowledge Transfer Programme.
intec's services
- Development of an interconnection code for fluctuating renewable based power integration based on technical, legal and commercial issues
- Development of a wheeling agreement for wheeling of fluctuating renewable power according to the current policy and regulatory framework
- Development and test of a model for the computation of wheeling losses
- Proposal for wheeler's grid availability performance guarantees and penalty measures for non-compliance
- Development of a knowledge transfer program
- Conducting two workshops on interconnection and wheeling issues.
Client
Electricity Regulatory Authority (ERA)Financing
KfW EntwicklungsbankPeriod of implementation
05.2016 - 01.2017
Rwanda, Burundi - Regional Interconnection Project (220 kV Transmission Line Kigoma - Butare - Ngozi - Gitega and 220/110 kV Substations)
The project was part of the NELSAP Regional Transmission Program that aimed at interconnecting five of the Nile Equatorial Lakes Countries, i.e. Burundi, DR Congo, Kenya, Rwanda and Uganda.
The project interconnected the electricity networks of Burundi and Rwanda through the construction of a new 220 kV single-circuit transmission line with a total length of 143 km. The line will initially be operated on the 110 kV level and might later be upgraded to 220 kV.
The project also included the construction of two new 220/110 kV substations, the extension of two existing 110 kV substations and the construction of 11.2 km of 30 kV line for rural electrification of Gisagara (Rwanda).
intec's services
- Review of existing feasibility studies
- Update of the Environmental and Social Management Plan (ESMP)
- Detailed design
- Preparation of complete tender documents for EPC Contractors (2 lots)
- Technical assistance during the procurement process, i.e. tendering, bid evaluation and contract award
- Preparation of a detailed Resettlement Action Plan (RAP) and monitoring of its implementation
- Design approval and supervision of implementation works
- Witnessing of factory acceptance tests, supervision of testing and commissioning
- Certification of Contractor's invoices and payments
- Monitoring and supervision of the implementation of the ESMP
- Safeguarding of project's compliance with KfW's and the World Bank's sustainability guidelines
- Technology transfer and training of employers' and project executing agency's staff
- Representation in the respective project steering and technical committees
Client
REGIDESO (Burundi), Energy Development Corporation Ltd. (Rwanda)Financing
KfW EntwicklungsbankPeriod of implementation
03.2015 - 06.2017Congo (RD) - Revision of the Studies on the 220 kV Line Kamanyola - Buhandahanda
The 220 kV Kamanyola - Buhandahanda line shall evacuate the electricity generated by the Ruzizi III Hydropower Plant which is part of the 220 kV interconnected network of the CEPGL (Communauté Economique des Pays des Grands Lacs - Economic Community of the Great Lake Countries). Studies for this line were finalised in September 2011 and shall be revised under the present project with the aim to take into consideration the new locations of the Kamanyola and Buhandahanda Substations and the new line concept.
intec's services
- Review of the project's technical feasibility, in particular through revision of the line's general concept (review of the line route and harmonisation of the design (double-circuit line with possibly only one single circuit operated in the first phase), study of the grid stability with the new line, set-up of a simulation model of the interconnected network, power distribution and load flow studies, review of the line protection system)
- Review of the project's economic and financial feasibility (cost estimates, economic and financial viability, proposals for project financing and implementation)
- Preparation of the detailed design for the revised line concept, elaboration of the longitudinal profile on the basis of satellite data, and tower spotting
- Preparation of an Environmental and Social Impact Assessment (ESIA) and an Environmental Management Plan (EMP) in conformity with international standards, and elaboration of a Resettlement Action Plan (RAP)
- Elaboration of the tender dossier
- Organisation of a validation seminar with EGL, SNEL (National Power Company of Congo), the Steering Committee and KfW
- Participation in the project appraisal mission.
Client
Energie des Grands Lacs - EGLFinancing
KfW EntwicklungsbankPeriod of implementation
07.2015 - 03.2017Uganda - Interconnection Code & Wheeling Agreement
The preparation of an interconnection code and a wheeling agreement is part of the GET FiT Uganda Program, launched in May 2013 to promote private investment into renewable energy generation projects in Uganda.
The main purpose of program is to fast-track a portfolio of about 20-25 small-scale renewable energy generation projects (promoted by private developers with a total installed capacity of roughly 150 MW). The overall objective of the present assignment is to enable proper and full evacuation of embedded generators in the future, at allowable national and international techno-economic standards.
The project includes detailed technical and economic requirements for connecting generation facilities to the existing grid and will involve both interconnection and wheeling aspects.
For this purpose, the following work packages constitute the framework of the project:
Part A - Work Package 1: Interconnection and Grid Code for fluctuating renewable energy power integration into the grid
Part B - Work Package 2: Wheeling Agreement for fluctuating renewable energy power wheeling
Part C - Work Package 3: Knowledge Transfer Programme.
intec's services
- Development of an interconnection code for fluctuating renewable based power integration based on technical, legal and commercial issues
- Development of a wheeling agreement for wheeling of fluctuating renewable power according to the current policy and regulatory framework
- Development and test of a model for the computation of wheeling losses
- Proposal for wheeler's grid availability performance guarantees and penalty measures for non-compliance
- Development of a knowledge transfer program
- Conducting two workshops on interconnection and wheeling issues.
Client
Electricity Regulatory Authority (ERA)Financing
KfW EntwicklungsbankPeriod of implementation
05.2016 - 01.2017-
Ghana - 330 kV Aboadze - Prestea Power Enhancement Project (APPEP)
Amandi Energy Solutions of Switzerland has a contract with the Ghana Grid Company Ltd. ("GRIDCO") for the Aboadze - Prestea Power Enhancement Project (APPEP) and contracted part of the design work to ROENG TEC and MPS.
The design services cover the extension with 8 bays (6 new and 2 existing) of the 330 kV Aboadze Substation.
intec's services
- Basic design of sections per typical bay, control building layout, civil works, and typical earthing design in-cluding calculation notes
- Drawing up of technical specifications, bills of quantity and other documents for tendering
- Technical opinion on received bids
- Detailed design and feasibility calculations for different options and coordination with GRIDCO
- Final detailed design drawings, update of the bills of quantities and final workshop drawings
- Technical assistance during the execution phase:upon request, design review and approval during project implementation, participation in factory acceptance test visits, if required
Client
Amandi Energy SolutionsFinancing
Amandi Energy SolutionsPeriod of implementation
04.2016 - 10.2016 -
Regional - Interconnexion Project CLSG (Phase 1)
The project included Owner's Engineer services for all pre-construction activities (tender documents, tendering, contract negotiations and award) for the construction of the following equipment:
- 1,303 km of 225 kV overhead line across the four countries, initially with one circuit on double circuit steel lattice towers, with OPGW,
- 12 new 225 kV substations, 1 in Côte d'Ivoire, 4 in Liberia, 5 in Sierra Leone and 2 in Guinea,
- installation of compensation equipment, static VAr compensators and shunt reactance in 5 substations,
- development of a control centre in Guinea including a regional SCADA system and frequency control systems, and extension of the NCC in Côte d'Ivoire,
- development of a frequency regulation study and procurement and installation of frequency control equipment.
Construction works are executed under 13 different EPC contracts.
intec's services
intec's experts contributed to the following tasks:
- Data collection and review of existing documentation,
- Review and finalisation of technical specifications and of prequalification and tender documents,
- Assistance during the tendering phase (invitations for prequalifications / tenders; evaluation of prequalifications and bid evaluation including respective reporting),
- Assistance in the finalisation of the EPC contracts (contract negotiations, preparation of contract documents),
- Review of project implementation schedules and preparation of the project implementation plan (PIP).
Client
WAPP Secretariat on behalf of TRANSCO CLSGFinancing
European Investment Bank (EIB) and World Bank (WB)Period of implementation
09.2014 - 12.2016 -
Ghana - 330 kV Aboadze - Prestea Power Enhancement Project (APPEP) - Design Services
Amandi Energy Solutions of Switzerland has a contract with the Ghana Grid Company Ltd. ("GRIDCO") for the Aboadze - Prestea Power Enhancement Project (APPEP) and contracted part of the design work to intec branch ROENG TEC .
The design services cover the 330 kV Aboadze - Prestea double-circuit overhead line.
intec's services
- Determination of operating principles, characterization and dimensions of the overhead line
- Preliminary design, including initial bills of quantities (BoQs)
- Feasibility calculations for the different options for the project, including costs, materials and equipment
- Final detailed design drawings including sag curve templates, tower spotting, etc.
- Soil investigation report
- Foundation design
- Coordination and planning; participation in monthly meetings, assistance during the implementation period, and overall supervision
- On-site training on construction of OHLs
Client
Amandi Energy SolutionsFinancing
Amandi Energy SolutionsPeriod of implementation
08.2014 - 09.2016
Ghana - 330 kV Aboadze - Prestea Power Enhancement Project (APPEP)
Amandi Energy Solutions of Switzerland has a contract with the Ghana Grid Company Ltd. ("GRIDCO") for the Aboadze - Prestea Power Enhancement Project (APPEP) and contracted part of the design work to ROENG TEC and MPS.
The design services cover the extension with 8 bays (6 new and 2 existing) of the 330 kV Aboadze Substation.
intec's services
- Basic design of sections per typical bay, control building layout, civil works, and typical earthing design in-cluding calculation notes
- Drawing up of technical specifications, bills of quantity and other documents for tendering
- Technical opinion on received bids
- Detailed design and feasibility calculations for different options and coordination with GRIDCO
- Final detailed design drawings, update of the bills of quantities and final workshop drawings
- Technical assistance during the execution phase:upon request, design review and approval during project implementation, participation in factory acceptance test visits, if required
Client
Amandi Energy SolutionsFinancing
Amandi Energy SolutionsPeriod of implementation
04.2016 - 10.2016Regional - Interconnexion Project CLSG (Phase 1)
The project included Owner's Engineer services for all pre-construction activities (tender documents, tendering, contract negotiations and award) for the construction of the following equipment:
- 1,303 km of 225 kV overhead line across the four countries, initially with one circuit on double circuit steel lattice towers, with OPGW,
- 12 new 225 kV substations, 1 in Côte d'Ivoire, 4 in Liberia, 5 in Sierra Leone and 2 in Guinea,
- installation of compensation equipment, static VAr compensators and shunt reactance in 5 substations,
- development of a control centre in Guinea including a regional SCADA system and frequency control systems, and extension of the NCC in Côte d'Ivoire,
- development of a frequency regulation study and procurement and installation of frequency control equipment.
Construction works are executed under 13 different EPC contracts.
intec's services
intec's experts contributed to the following tasks:
- Data collection and review of existing documentation,
- Review and finalisation of technical specifications and of prequalification and tender documents,
- Assistance during the tendering phase (invitations for prequalifications / tenders; evaluation of prequalifications and bid evaluation including respective reporting),
- Assistance in the finalisation of the EPC contracts (contract negotiations, preparation of contract documents),
- Review of project implementation schedules and preparation of the project implementation plan (PIP).
Client
WAPP Secretariat on behalf of TRANSCO CLSGFinancing
European Investment Bank (EIB) and World Bank (WB)Period of implementation
09.2014 - 12.2016Ghana - 330 kV Aboadze - Prestea Power Enhancement Project (APPEP) - Design Services
Amandi Energy Solutions of Switzerland has a contract with the Ghana Grid Company Ltd. ("GRIDCO") for the Aboadze - Prestea Power Enhancement Project (APPEP) and contracted part of the design work to intec branch ROENG TEC .
The design services cover the 330 kV Aboadze - Prestea double-circuit overhead line.
intec's services
- Determination of operating principles, characterization and dimensions of the overhead line
- Preliminary design, including initial bills of quantities (BoQs)
- Feasibility calculations for the different options for the project, including costs, materials and equipment
- Final detailed design drawings including sag curve templates, tower spotting, etc.
- Soil investigation report
- Foundation design
- Coordination and planning; participation in monthly meetings, assistance during the implementation period, and overall supervision
- On-site training on construction of OHLs
Client
Amandi Energy SolutionsFinancing
Amandi Energy SolutionsPeriod of implementation
08.2014 - 09.2016-
Mali - PASE - Extension of EDM's Transmission and Distribution Networks
The project was part of the "PASE" (Project for the Support to the Energy Sector) for which the World Bank granted a loan to the Government of Mali. The project in general aimed at improving access to electricity, and efficiency in the supply and utilisation of electrical energy. The technical measures of the project included the following components:
- Extension of the MV/LV networks in Bamako and Kati,
- Construction of the 30 kV Kati Substation,
- Reinforcement and extension of the MV/LV networks in Kayes, Sikasso, Koutiala, and Ségou,
- Rehabilitation of the 150 kV lines Bamako - Fana and Fana - Ségou and restructuring of Fana substation connection from T-off to line-in line-out arrangement,
- Extension of the Kalabancoro Substation (transformer 60 MVA, 150/30 kV) and renewal of the 30/15 kV Sotuba Substation,
- Extension of the 15 kV SOGEM Substation in Kodialani and installation of 15 kV outgoing feeders,
- Installation of the second circuit on the 150 kV Kodialani - Sirakoro line.
intec's services
- Overall project management and home-office back-up support for specific tasks,
- Coordination of the detailed implementation plan with EDM,
- Approval of technical documents and implementation studies,
- Technical control of plans and documents,
- Factory acceptance tests, monitoring and control of manufacturing,
- Site supervision,
- Budget control and management,
- Implementation of the quality management plan and the health and safety plans,
- Verification of the environmental protection plan,
- Reporting.
Client
Energie du Mali S.A. (EDM)Financing
International Development Association (IDA)Period of implementation
02.2014 - 07.2016 -
Bangladesh - New 132/33 GIS substations, a new cable system and a 4-circuit 132 kV transmission line
The project shall contribute to the Sustainable Power Sector Development Program II by securing proper voltage levels, and thus reducing transmission losses. This improvement of the transmission system is necessary to achieve a sustainable restructuring of the power sector. The project includes the following measures:
- Lot 1 - Substations: Construction of new 132/33 kV GIS substations at Lalbagh and Madertak, and conversion of 132/33 kV Dhanmodi transformer station into a regular substation, including construction of an additional 132 kV bay (one and a half breaker scheme) at Rampura Substation
- Lot 2 - Cable system: Construction of a new 132 and 33 kV underground cable system
- Lot 3 -Transmission lines: Construction of 4-circuit 132 kV overhead transmission lines, including a river crossing
intec's services
- Assistance to PIU in evaluation of bids; Formulation of notice of award recommendation
- Assistance in contract negotiations
- Control of contractor's time schedule
- Assist contractor in obtaining permits and way leave rights
- Approval of Contractor's/Suppliers' design
- Participation in factory acceptance tests
- Approval of final design and as built design
- Supervision of construction
- Budget control and review of invoices
- Monitoring of training programme
- Assistance to PIU in establishing an operations and maintenance concept
- Assistance in commissioning and assistance during defects liability and warranty period
Client
Dhaka Power Distribution Company Ltd. (DPDC)Financing
KfW EntwicklungsbankPeriod of implementation
06.2009 - 06.2016 -
Albania/Kosovo - 400 kV Transmission Line Albania - Kosovo (Tirana - Pristine)
Consulting services for:
- Component 1 (Albania): Construction of a 400 kV transmission line between Tirana and the Kosovo border, and extension of a 400/230/110 kV substation by one complete 400 kV feeder;
- Component 2 (Kosovo): Construction of a 400 kV transmission line from 400/230/110 kV substation Ko-sovo B to the border to Albania, and extension of the existing substation Kosovo B by one complete 400 kV feeder;
- Additional services for TSO service contract between OST and KOSTT;
- Additional services for the extension of the Substation of HPP Koman (Albania) (separate reference)
intec's services
Phase 1
- Review of technical concept, data collection, reconstruction of missing drawings
- Assistance to OST and KOSTT in the routing of the line
- Detailed line route survey incl. tower pegging and preliminary design of towers
- Preparation of preliminary planning / schedule of supplies and services, review of the cost calculation
- Support to the clients on permits and licences, rights of way and land use
- Full environmental impact assessment (EIA)
- Preparation of tender documents for goods and services (technical and commercial)
- Support during the tender process (launching of tender, evaluation of bids, contract negotiations)
- Addendum: Retendering of Lot 1 of the Albanian Part (Tirana - Morina)
Phase 2
- Design approval, participation in FATs; supervision of dismantling works
- Monitoring of the quality of the construction and installation works
- Monitoring of project cost / processing Contractor's invoices
- Support to the clients in elaborating an O&M concept
- Monitoring of commissioning / commencement of commercial operation
- Consulting services during "Defects Liability Period"
- Assist the clients in elaborating the final appraisal report
Additional services for TSO Contract:- Drafting of a sample transmission system operator (TSO) service contract between OST and KOSTT
Client
Albanian Transmission System Operator (OST) Transmission, System and Market Operator J.S.C. (KOSTT)Financing
Kreditanstalt für Wiederaufbau (KfW)Period of implementation
10.2009 - 06.2016
Mali - PASE - Extension of EDM's Transmission and Distribution Networks
The project was part of the "PASE" (Project for the Support to the Energy Sector) for which the World Bank granted a loan to the Government of Mali. The project in general aimed at improving access to electricity, and efficiency in the supply and utilisation of electrical energy. The technical measures of the project included the following components:
- Extension of the MV/LV networks in Bamako and Kati,
- Construction of the 30 kV Kati Substation,
- Reinforcement and extension of the MV/LV networks in Kayes, Sikasso, Koutiala, and Ségou,
- Rehabilitation of the 150 kV lines Bamako - Fana and Fana - Ségou and restructuring of Fana substation connection from T-off to line-in line-out arrangement,
- Extension of the Kalabancoro Substation (transformer 60 MVA, 150/30 kV) and renewal of the 30/15 kV Sotuba Substation,
- Extension of the 15 kV SOGEM Substation in Kodialani and installation of 15 kV outgoing feeders,
- Installation of the second circuit on the 150 kV Kodialani - Sirakoro line.
intec's services
- Overall project management and home-office back-up support for specific tasks,
- Coordination of the detailed implementation plan with EDM,
- Approval of technical documents and implementation studies,
- Technical control of plans and documents,
- Factory acceptance tests, monitoring and control of manufacturing,
- Site supervision,
- Budget control and management,
- Implementation of the quality management plan and the health and safety plans,
- Verification of the environmental protection plan,
- Reporting.
Client
Energie du Mali S.A. (EDM)Financing
International Development Association (IDA)Period of implementation
02.2014 - 07.2016Bangladesh - New 132/33 GIS substations, a new cable system and a 4-circuit 132 kV transmission line
The project shall contribute to the Sustainable Power Sector Development Program II by securing proper voltage levels, and thus reducing transmission losses. This improvement of the transmission system is necessary to achieve a sustainable restructuring of the power sector. The project includes the following measures:
- Lot 1 - Substations: Construction of new 132/33 kV GIS substations at Lalbagh and Madertak, and conversion of 132/33 kV Dhanmodi transformer station into a regular substation, including construction of an additional 132 kV bay (one and a half breaker scheme) at Rampura Substation
- Lot 2 - Cable system: Construction of a new 132 and 33 kV underground cable system
- Lot 3 -Transmission lines: Construction of 4-circuit 132 kV overhead transmission lines, including a river crossing
intec's services
- Assistance to PIU in evaluation of bids; Formulation of notice of award recommendation
- Assistance in contract negotiations
- Control of contractor's time schedule
- Assist contractor in obtaining permits and way leave rights
- Approval of Contractor's/Suppliers' design
- Participation in factory acceptance tests
- Approval of final design and as built design
- Supervision of construction
- Budget control and review of invoices
- Monitoring of training programme
- Assistance to PIU in establishing an operations and maintenance concept
- Assistance in commissioning and assistance during defects liability and warranty period
Client
Dhaka Power Distribution Company Ltd. (DPDC)Financing
KfW EntwicklungsbankPeriod of implementation
06.2009 - 06.2016Albania/Kosovo - 400 kV Transmission Line Albania - Kosovo (Tirana - Pristine)
Consulting services for:
- Component 1 (Albania): Construction of a 400 kV transmission line between Tirana and the Kosovo border, and extension of a 400/230/110 kV substation by one complete 400 kV feeder;
- Component 2 (Kosovo): Construction of a 400 kV transmission line from 400/230/110 kV substation Ko-sovo B to the border to Albania, and extension of the existing substation Kosovo B by one complete 400 kV feeder;
- Additional services for TSO service contract between OST and KOSTT;
- Additional services for the extension of the Substation of HPP Koman (Albania) (separate reference)
intec's services
Phase 1
- Review of technical concept, data collection, reconstruction of missing drawings
- Assistance to OST and KOSTT in the routing of the line
- Detailed line route survey incl. tower pegging and preliminary design of towers
- Preparation of preliminary planning / schedule of supplies and services, review of the cost calculation
- Support to the clients on permits and licences, rights of way and land use
- Full environmental impact assessment (EIA)
- Preparation of tender documents for goods and services (technical and commercial)
- Support during the tender process (launching of tender, evaluation of bids, contract negotiations)
- Addendum: Retendering of Lot 1 of the Albanian Part (Tirana - Morina)
Phase 2
- Design approval, participation in FATs; supervision of dismantling works
- Monitoring of the quality of the construction and installation works
- Monitoring of project cost / processing Contractor's invoices
- Support to the clients in elaborating an O&M concept
- Monitoring of commissioning / commencement of commercial operation
- Consulting services during "Defects Liability Period"
- Assist the clients in elaborating the final appraisal report
Additional services for TSO Contract:
- Drafting of a sample transmission system operator (TSO) service contract between OST and KOSTT