Projects worldwide
intec has executed and is implementing large and complex projects in nearly all regions of the world.
The projects listed on the website represent only a selection of our project references.
Our projects
-
Guinea - Linsan - Fomi Transmission Line (CLSG / Rural Electrification Component Guinea) 1,214,110 Euro (1,303,590 US$) Financing: African Development Bank (AfDB)
The Linsan - Fomi transmission line project is one of the priority projects identified in the electrification masterplan of Guinea. The implementation of this line aims at ensuring a stable integration of the national electricity networks of the ECOWAS member countries. At the same time, it serves to evacuate the power produced by the Kaleta Power Plant, the projected Souapiti HPP and other power plants to come.
The project covers the construction of approx. 394 km of 225 kV double-circuit transmission line between Linsan, Dabola, Kouroussa and Fomi with four associated 225 kV substations. It covers the following tasks:
- Line routing and production of maps, plans and profile drawings,
- Environmental and Social Impact Assessment (ESIA),
- Elaboration of the Environmental and Social Management Plan (ESMP),
- Elaboration of the Resettlement Action Plan (RAP),
- Feasibility study for the line,
- Preparation of functional prequalification and tender documents,
- Training.
intec's services
Line routing and production of maps, plans and profile drawings;
Feasibility study, including:
- Technical interconnection study,
- Economic, financial and sensitivity analyses and tariff proposal ,
- Risk analyses,
- Training for the representatives of the projectparticipating parties on design of line interconnection and of transformer substations, and on the implementation of technical, economic and financial analyses,
- Design and technical specifications for the line and the substations,
- Preparation of functional prequalification and tender documents, and bid packaging.
Client
Electricité de Guinée (EDG)Financing
African Development Bank (AfDB)Period of implementation
5.4.2017 - 4.2.2018 -
Guinea - Analysis of Electricity Supply solutions in the region of Boke
MASDAR is developing various projects in the Caribbean and other regions of the world and sourced experts to support the engineering and project management team. These support tasks are contracted separately in the form of so-called Work Orders (WO).
The Guinea Alumina Company (GAC) currently plans to extract about 15 million tons bauxite per year and to install approximately 30 MW of power capacity. The government and other key stakeholders are keen to develop power supply solutions for both the mining sector and the civil / private sector. In light of this, the present study defines the demand and potential power supply options for mining activities and for the surrounding communities.
The overall objectives of this assignment were to:
- Prepare a demand study on the power requirements for the short, medium and long term in the regions impacted by GAC´s activities.
- Develop options, incorporating both renewable energy and existing (and new) fossil fuel based generation for meeting the determined power requirements.
intec's services
- Data collation and initial analyses (initially desktop focused)
- Site visits and meetings with key stakeholders
- Tour and inspection of available facilities
- Development of project concept and options
- Feasibility report, incorporating demand study outcomes
Client
Abu Dhabi Future Energy Company - MASDARFinancing
Abu Dhabi Future Energy Company - MASDARPeriod of implementation
10/2017 - 01/2018 -
Albania - 400 kV Extension of Koman HPP Substation
The project is an additional component of the overall project "400 kV Transmission Line Albania - Kosovo" and includes all required services for the extension of the 220 kV Koman Hydropower Plant Substation by a 400 kV part.
intec's services
- Assessment of technical feasibility and report
- ESIA study and report
- Elaboration of technical specifications and tender documents
- Assistance to OST during the bidding period
- Bid evaluation
- Assistance to OST in contract negotiation and award of the EPC contract
- Review and approval of design
- Supervision of procurement, manufacturing and transportation
- Supervision of construction and installation works
- Testing, commissioning and taking-over
Client
Albanian Transmission System Operator (OST)Financing
Kreditanstalt für Wiederaufbau (KfW)Period of implementation
1.1.2016 - 31.1.2018
Guinea - Linsan - Fomi Transmission Line (CLSG / Rural Electrification Component Guinea) 1,214,110 Euro (1,303,590 US$) Financing: African Development Bank (AfDB)
The Linsan - Fomi transmission line project is one of the priority projects identified in the electrification masterplan of Guinea. The implementation of this line aims at ensuring a stable integration of the national electricity networks of the ECOWAS member countries. At the same time, it serves to evacuate the power produced by the Kaleta Power Plant, the projected Souapiti HPP and other power plants to come.
The project covers the construction of approx. 394 km of 225 kV double-circuit transmission line between Linsan, Dabola, Kouroussa and Fomi with four associated 225 kV substations. It covers the following tasks:
- Line routing and production of maps, plans and profile drawings,
- Environmental and Social Impact Assessment (ESIA),
- Elaboration of the Environmental and Social Management Plan (ESMP),
- Elaboration of the Resettlement Action Plan (RAP),
- Feasibility study for the line,
- Preparation of functional prequalification and tender documents,
- Training.
intec's services
Line routing and production of maps, plans and profile drawings;
Feasibility study, including:
- Technical interconnection study,
- Economic, financial and sensitivity analyses and tariff proposal ,
- Risk analyses,
- Training for the representatives of the projectparticipating parties on design of line interconnection and of transformer substations, and on the implementation of technical, economic and financial analyses,
- Design and technical specifications for the line and the substations,
- Preparation of functional prequalification and tender documents, and bid packaging.
Client
Electricité de Guinée (EDG)Financing
African Development Bank (AfDB)Period of implementation
5.4.2017 - 4.2.2018Guinea - Analysis of Electricity Supply solutions in the region of Boke
MASDAR is developing various projects in the Caribbean and other regions of the world and sourced experts to support the engineering and project management team. These support tasks are contracted separately in the form of so-called Work Orders (WO).
The Guinea Alumina Company (GAC) currently plans to extract about 15 million tons bauxite per year and to install approximately 30 MW of power capacity. The government and other key stakeholders are keen to develop power supply solutions for both the mining sector and the civil / private sector. In light of this, the present study defines the demand and potential power supply options for mining activities and for the surrounding communities.
The overall objectives of this assignment were to:
- Prepare a demand study on the power requirements for the short, medium and long term in the regions impacted by GAC´s activities.
- Develop options, incorporating both renewable energy and existing (and new) fossil fuel based generation for meeting the determined power requirements.
intec's services
- Data collation and initial analyses (initially desktop focused)
- Site visits and meetings with key stakeholders
- Tour and inspection of available facilities
- Development of project concept and options
- Feasibility report, incorporating demand study outcomes
Client
Abu Dhabi Future Energy Company - MASDARFinancing
Abu Dhabi Future Energy Company - MASDARPeriod of implementation
10/2017 - 01/2018Albania - 400 kV Extension of Koman HPP Substation
The project is an additional component of the overall project "400 kV Transmission Line Albania - Kosovo" and includes all required services for the extension of the 220 kV Koman Hydropower Plant Substation by a 400 kV part.
intec's services
- Assessment of technical feasibility and report
- ESIA study and report
- Elaboration of technical specifications and tender documents
- Assistance to OST during the bidding period
- Bid evaluation
- Assistance to OST in contract negotiation and award of the EPC contract
- Review and approval of design
- Supervision of procurement, manufacturing and transportation
- Supervision of construction and installation works
- Testing, commissioning and taking-over
Client
Albanian Transmission System Operator (OST)Financing
Kreditanstalt für Wiederaufbau (KfW)Period of implementation
1.1.2016 - 31.1.2018-
Germany - Biomass Cogeneration Plant Melsungen
M/s. HolzHeizKraftWerk Melsungen GmbH & Co. KG intends to construct a biomass-fuelled combined heat and power plant in the city of Melsungen financed by a Consortium under the leadership of Deutsche Anlagen Leasing (DAL).
The CHP has the following technical features:
- 3.5 MWel
- 9.8 MWth
- 33,000 t(atro)/year fuel consumption
- 21 MW fuel input
Overall investment is in the magnitude of 32.6 million Euros.
The produced heat and process steam will be fed into the network of a nearby company. The produced electricity will be fed to the public grid as per the German renewable energy feed-in tariff ("EEG").
M/s. HolzHeizKraftWerk Melsungen GmbH & Co. KG assigned Lahmeyer International GmbH as a Lender's Engineer and intec works as a subcontractor to Lahmeyer International.
intec's services
Consulting services during the construction phase, i.e.
- Assessment of the quarterly progress reports
- Assessment of payment milestones
Verification during handing over phase, i.e.
- Completion of major works
- Trial runs and acceptance tests
- Provisional and final acceptance
- Asbuilt documentation
- Permits and licenses
Client
Lahmeyer International GmbHFinancing
Lahmeyer International GmbHPeriod of implementation
14.2.2014 - 31.12.2017 -
ECOWAS Region - Support to RE Flagship Projects
ECOWAS, the Economic Community of West African states, comprises 15 West African countries: Benin, Burkina Faso, Cabo Verde, Côte d'Ivoire, Gambia, Ghana, Guinea, Guinea-Bissau, Liberia, Mali, Niger, Nigeria, Senegal, Sierra Leone and Togo. The overall GIZ project supports the regional dissemination of experience concerning renewable energies and aims at improving the capacities of utilities in the long term.
Output Area B of the project "Generation - RE flagship projects" follows a two-pronged approach:
- Documentation of information on and experience with existing RE flagship projects;
- Support to the development of planned projects through technical assistance for project development and transaction advice, accompanied by documentation of experience.
intec's services
Provision and coordination of a pool of short-term experts to carry out the following tasks:
- Support to ECREEE in the process of screening, evaluating and prioritizing RE projects or promotion schemes
- Support to project developers and government representatives on technical, legal, financial and economic aspects of selected projects.
- Monitoring of selected projects during critical phases of their development and reporting of required action.
- Compilation of experiences with the selected projects and support to ECREEE / other institutions in the region in the dissemination of key findings and lessons learnt.
- Assistance to ECREEE and GIZ in supporting selected ECOWAS member states in creating an enabling legal, regulatory and administrative framework for grid-connected RE projects.
The above tasks cover PV, wind, small hydropower and biomass technology.
Client
ECREEE - ECOWAS Centre for Renewable Energy and Energy EfficiencyFinancing
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHPeriod of implementation
01.04.2015 - 15.12.2017 -
Uganda - Mutundwe - Entebbe 132 kV Power Transmission Line and Related Substation Works
The project scope comprises the following:
- Construction of approximately 36 km of double circuit 132 kV transmission line between Mutundwe Substation near Kampala City and Entebbe, partly with 4 circuits and with OPGW on one circuit.
- Extension of the existing 132/33/11 kV Mutundwe Substation (two outgoing 132 kV feeders, extension of busbar system; extension/modification of protection, control, telecommunication, and auxiliary AC/DC power supply systems; civil works).
- Entebbe Substation: Construction of a new outdoor 132/33 kV substation and 33 kV indoor switchgear (double busbar system, two incoming 132 kV line feeders, two 132/33 kV transformer bays with 50 MVA power transformers, one bus coupler bay, protection, control and SCADA, telecommunication and auxiliary power supply equipment, 33 kV indoor switchgear with two incoming and six outgoing feeders, a connection by 33 kV underground cable to the existing 33/11 kV distribution; control building, all related civil works).
intec's services
Project Design and Preparation of Tender Documents:
Review of the 2011 feasibility study report; review and adjustment of line route; pegging of angle towers; power system analysis with PSS/E; soil test report and project design report; elaboration of design and technical specifications for transmission line and substations; preparation of tender documents for EPC contracting.Assistance during the Tendering Stage:
Lead of pre-bid meeting and site visit with Bidders; Bidder's clarifications; bid evaluation; post-tender clarifications; preparation of evaluation report; assistance during contract negotiations; preparation of EPC contracts.Project Management and Construction Supervision:
Review and approval of design calculations and drawings; factory acceptance and site tests; supervision of works on site; monitoring of time schedule; project cost control; processing of contractors' invoices; monitoring of environmental management plan and of the adherence of the social impact assessment recommendations; enforcement of contractor's health; safety and environmental manual; witnessing of commissioning tests; preparation of commissioning protocol; punch list; preparation of final inspection and formal takeover; review of as-built drawings; preparation of project reports.Follow-up during the two-year Defects Liability Period (DLP).
Training of Client's Personnel:
On-the-job training of electrical and civil engineers on power system analysis and design, on the preparation of specifications for transmission lines and substations and on supervision of construction works; elaboration of a detailed training programme and delivery of a 3-week training session for Client's Engineers in the Consultant's home office.
Client
Uganda Electricity Transmission Company Ltd. (UETCL)Financing
Kreditanstalt für Wiederaufbau (KfW)Period of implementation
26.3.2014 - 30.11.2017
Germany - Biomass Cogeneration Plant Melsungen
M/s. HolzHeizKraftWerk Melsungen GmbH & Co. KG intends to construct a biomass-fuelled combined heat and power plant in the city of Melsungen financed by a Consortium under the leadership of Deutsche Anlagen Leasing (DAL).
The CHP has the following technical features:
- 3.5 MWel
- 9.8 MWth
- 33,000 t(atro)/year fuel consumption
- 21 MW fuel input
Overall investment is in the magnitude of 32.6 million Euros.
The produced heat and process steam will be fed into the network of a nearby company. The produced electricity will be fed to the public grid as per the German renewable energy feed-in tariff ("EEG").
M/s. HolzHeizKraftWerk Melsungen GmbH & Co. KG assigned Lahmeyer International GmbH as a Lender's Engineer and intec works as a subcontractor to Lahmeyer International.
intec's services
Consulting services during the construction phase, i.e.
- Assessment of the quarterly progress reports
- Assessment of payment milestones
Verification during handing over phase, i.e.
- Completion of major works
- Trial runs and acceptance tests
- Provisional and final acceptance
- Asbuilt documentation
- Permits and licenses
Client
Lahmeyer International GmbHFinancing
Lahmeyer International GmbHPeriod of implementation
14.2.2014 - 31.12.2017ECOWAS Region - Support to RE Flagship Projects
ECOWAS, the Economic Community of West African states, comprises 15 West African countries: Benin, Burkina Faso, Cabo Verde, Côte d'Ivoire, Gambia, Ghana, Guinea, Guinea-Bissau, Liberia, Mali, Niger, Nigeria, Senegal, Sierra Leone and Togo. The overall GIZ project supports the regional dissemination of experience concerning renewable energies and aims at improving the capacities of utilities in the long term.
Output Area B of the project "Generation - RE flagship projects" follows a two-pronged approach:
- Documentation of information on and experience with existing RE flagship projects;
- Support to the development of planned projects through technical assistance for project development and transaction advice, accompanied by documentation of experience.
intec's services
Provision and coordination of a pool of short-term experts to carry out the following tasks:
- Support to ECREEE in the process of screening, evaluating and prioritizing RE projects or promotion schemes
- Support to project developers and government representatives on technical, legal, financial and economic aspects of selected projects.
- Monitoring of selected projects during critical phases of their development and reporting of required action.
- Compilation of experiences with the selected projects and support to ECREEE / other institutions in the region in the dissemination of key findings and lessons learnt.
- Assistance to ECREEE and GIZ in supporting selected ECOWAS member states in creating an enabling legal, regulatory and administrative framework for grid-connected RE projects.
The above tasks cover PV, wind, small hydropower and biomass technology.
Client
ECREEE - ECOWAS Centre for Renewable Energy and Energy EfficiencyFinancing
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbHPeriod of implementation
01.04.2015 - 15.12.2017Uganda - Mutundwe - Entebbe 132 kV Power Transmission Line and Related Substation Works
The project scope comprises the following:
- Construction of approximately 36 km of double circuit 132 kV transmission line between Mutundwe Substation near Kampala City and Entebbe, partly with 4 circuits and with OPGW on one circuit.
- Extension of the existing 132/33/11 kV Mutundwe Substation (two outgoing 132 kV feeders, extension of busbar system; extension/modification of protection, control, telecommunication, and auxiliary AC/DC power supply systems; civil works).
- Entebbe Substation: Construction of a new outdoor 132/33 kV substation and 33 kV indoor switchgear (double busbar system, two incoming 132 kV line feeders, two 132/33 kV transformer bays with 50 MVA power transformers, one bus coupler bay, protection, control and SCADA, telecommunication and auxiliary power supply equipment, 33 kV indoor switchgear with two incoming and six outgoing feeders, a connection by 33 kV underground cable to the existing 33/11 kV distribution; control building, all related civil works).
intec's services
Project Design and Preparation of Tender Documents:
Review of the 2011 feasibility study report; review and adjustment of line route; pegging of angle towers; power system analysis with PSS/E; soil test report and project design report; elaboration of design and technical specifications for transmission line and substations; preparation of tender documents for EPC contracting.
Assistance during the Tendering Stage:
Lead of pre-bid meeting and site visit with Bidders; Bidder's clarifications; bid evaluation; post-tender clarifications; preparation of evaluation report; assistance during contract negotiations; preparation of EPC contracts.
Project Management and Construction Supervision:
Review and approval of design calculations and drawings; factory acceptance and site tests; supervision of works on site; monitoring of time schedule; project cost control; processing of contractors' invoices; monitoring of environmental management plan and of the adherence of the social impact assessment recommendations; enforcement of contractor's health; safety and environmental manual; witnessing of commissioning tests; preparation of commissioning protocol; punch list; preparation of final inspection and formal takeover; review of as-built drawings; preparation of project reports.
Follow-up during the two-year Defects Liability Period (DLP).
Training of Client's Personnel:
On-the-job training of electrical and civil engineers on power system analysis and design, on the preparation of specifications for transmission lines and substations and on supervision of construction works; elaboration of a detailed training programme and delivery of a 3-week training session for Client's Engineers in the Consultant's home office.