U.A.E. - Project examples
-
UAE - Dubai EXPO 2020 - Design and Construction Supervision Consultancy Services
In 2020, the UAE will host the Expo 2020 in Dubai, which site is located adjacent to Al Makthoum International Airport and between Abu Dhabi International Airport and Dubai International Airport. The site covers a total area of 4.38 km², and will have the capacity to accommodate up to 300,000 visitors per day and a total of 25 million visitors.
The sustainability and renewable energy mix based concepts in this project cover various aspects related to rental and/or temporary access to building roofs for installation of Solar PV panels (BIPV, BAPV) during Expo 2020 Dubai's six-month event period and most flexible concepts for renewable energy systems integrated into other projects. The portfolio of renewable energy assets considered in this project contains solar PV, Waste-to-Energy anaerobic digestion, wind energy, solar hot water, fuel cells, energy storage, solar cooling, and/or other future RE technologies, e.g. transportation concepts for e-mobility to be deployed along with a smart grid infrastructure.
intec's services
The scope covers the following stages for integration of renewable energy to meet sustainability targets, considering the terms and practices set forth in RIBA (Royal Institute of British Architectures) through all stages as detailed below:
STAGE 1: Master Plan Validation and Review and Feasibility Study:
- Master Plan validation to guide the planning process for the integration of renewable energy technologies through careful evaluation of the current Master Plan in order to ensure that the targets (Sustainability KPIs) of the Dubai Expo are met
- Development of Renewable Energy Strategy for the Expo Development in line with EXPO guiding principles
- Authority and stakeholder coordination and Interface management
- Technical and Financial Feasibility Study of Solar PV and other Renewable Energy systems on the Expo development covering:
- Elaboration of a financial model, including all CAPEX, OPEX, COF, ROI, payback periods, all other project related outlay costs, and any revenue that may be realized by feed-in tariff arrangements
- Review of the options for project delivery model (e.g. a DBO variant or EPC)
- Review of the best equity model
- A life-cycle comparison of different quantities of Renewable Energy assets in each of the above areas of the Expo development, reviewing energy, carbon and cost over a suitable life cycle
- A life-cycle comparison of different solar panel material
- Review of any upper limit of roof mounted solar PV assets due to excessive building structural loads
- Review of the legal environment including land use (ownership, lease) and operating license regimes for power generation assets
STAGE 2 : Concept Design:
- Site wide conceptual design for each of the selected renewable energy assets on EXPO site including their interconnectivity to distribution network and utility grid
- Coordination with building designers to ensure adequate levels of renewable energy to achieve the KPIs
- Updating of Project Design Management Plan (DMP), Project Execution Programme (PEP),Project Quality Plan (PQP)
- Undertake risk, value management and constructability reviews
- Update the Authority Approval Strategy, review and update the Procurement Strategy, submissions to Local Authorities and obtaining approvals
STAGE 3a: ER Requirements and Design Guidelines
- Provision of Employer’s Requirements for temporary and permanent Renewable Energy assets (as appropriate); EPC, FIDIC DBO, BOT, BOO or other, including suitable power production performance guarantees
- Provision of Design Guidelines for temporary and permanent Renewable Energy assets (as appropriate)
STAGE 3b: Developed Design
- Develop and refine the approved Stage 2 – Concept Design, incorporating value engineering
- Undertake risk, value engineering and constructability workshop(s),update the Authority Approval Strategy
- Review and finalize the RE Procurement Strategy
STAGE 4 : Technical Design and Tender Services
- Design all facilities required for a complete RE system in line with DBO and EPC Employer’s Requirements
- Preparation of drawings for each Stage submission as well as Tender Documents and IFC Documents
- Management of pre-qualification / shortlisting of EPC /DBO tenderers and technology suppliers
- Evaluation of tenderers’ technical offers and preparation of Tender Technical Evaluation Report
- Assistance in negotiations with the tenderers and in the award of the Construction Contract(s)
- Advisory services on the appointment of the Contractor and on the responsibilities of the contracting parties and the Engineer
- Obtaining approval of the IFC Documents for issuance to Contractor
STAGE 5a: Construction Supervision: mobilization, contract administration and site supervision services during 28 months period of construction for the Renewable Energy Works including monitoring and approving of the testing and commissioning of the Project
STAGE 5b: Sustainability Audit Services : Review the projects through design development and construction phases and confirm whether the projects are contributing to the Expo 2020 sustainability KPIs
STAGE 6 : Post Practical Completion (Defects Liability Period): Checking the operational conditions and the compliance of the Works with the requirements of the Construction Contract(s), Conducting regular visits to the Project to supervise the completion of the outstanding Works
Client
Bureau EXPO Dubai 2020Financing
Bureau EXPO Dubai 2020Period of implementation
04.2016 - 10.2021 -
Oman - 50 MW Wind Power Plant in Dhofar
Abu Dhabi Future Energy Company - Masdar is developing a 50 MW Wind Power Plant in Dhofar Governorate in the Saltant of Oman. The project consists of 13 turbines of the state-of-art GE wind technology, 2 substations and 13km OHL. The Project design, supply, construction and commissioning was awarded to an IPC consortium. The main stakeholders of this wind farm are RAECO as the future operator, OETC as the owner of the electricity transmission line and one substation, and OPWP as the procurer of the generated electricity from this wind power plant.
intec's services
Work Package 1: Assistance in bid evaluation (EPC and O&M):
- Evaluation of technical responsiveness, of the energy yield calculations provided in the bids, the proposed project schedule, warranties, deviations, and the O&M strategy
- Provision of technical support during contract negotiations
- Assistance in the preparation of the contract documents
Work Package 2: Project management consultancy services for design review, material approval, construction management and works supervision:
- Review of the power purchase agreement (PPA) and the transmission connection agreement (TCA)
- Review and approval of design
- Witnessing of FATs for the 132 kV OHL equipment, the 132 and 33 kV switchgears, the 132/33 kV power and auxiliary transformers, the wind energy converters and associated equipment, the cabling, and the protection and SCADA systems
- Monitoring of environmental management and health and safety plans
- Construction management and works supervision, and assistance in commissioning
Client
Abu Dhabi Future Energy Company – MASDARPeriod of implementation
04.2015 - 07.2019 -
Guinea - Analysis of Electricity Supply solutions in the region of Boke
MASDAR is developing various projects in the Caribbean and other regions of the world and sourced experts to support the engineering and project management team. These support tasks are contracted separately in the form of so-called Work Orders (WO).
The Guinea Alumina Company (GAC) currently plans to extract about 15 million tons bauxite per year and to install approximately 30 MW of power capacity. The government and other key stakeholders are keen to develop power supply solutions for both the mining sector and the civil / private sector. In light of this, the present study defines the demand and potential power supply options for mining activities and for the surrounding communities.
The overall objectives of this assignment were to:
- Prepare a demand study on the power requirements for the short, medium and long term in the regions impacted by GAC´s activities.
- Develop options, incorporating both renewable energy and existing (and new) fossil fuel based generation for meeting the determined power requirements.
intec's services
- Data collation and initial analyses (initially desktop focused)
- Site visits and meetings with key stakeholders
- Tour and inspection of available facilities
- Development of project concept and options
- Feasibility report, incorporating demand study outcomes
Client
Abu Dhabi Future Energy Company - MASDARFinancing
Abu Dhabi Future Energy Company - MASDARPeriod of implementation
10/2017 - 01/2018
UAE - Dubai EXPO 2020 - Design and Construction Supervision Consultancy Services
In 2020, the UAE will host the Expo 2020 in Dubai, which site is located adjacent to Al Makthoum International Airport and between Abu Dhabi International Airport and Dubai International Airport. The site covers a total area of 4.38 km², and will have the capacity to accommodate up to 300,000 visitors per day and a total of 25 million visitors.
The sustainability and renewable energy mix based concepts in this project cover various aspects related to rental and/or temporary access to building roofs for installation of Solar PV panels (BIPV, BAPV) during Expo 2020 Dubai's six-month event period and most flexible concepts for renewable energy systems integrated into other projects. The portfolio of renewable energy assets considered in this project contains solar PV, Waste-to-Energy anaerobic digestion, wind energy, solar hot water, fuel cells, energy storage, solar cooling, and/or other future RE technologies, e.g. transportation concepts for e-mobility to be deployed along with a smart grid infrastructure.
intec's services
The scope covers the following stages for integration of renewable energy to meet sustainability targets, considering the terms and practices set forth in RIBA (Royal Institute of British Architectures) through all stages as detailed below:
STAGE 1: Master Plan Validation and Review and Feasibility Study:
- Master Plan validation to guide the planning process for the integration of renewable energy technologies through careful evaluation of the current Master Plan in order to ensure that the targets (Sustainability KPIs) of the Dubai Expo are met
- Development of Renewable Energy Strategy for the Expo Development in line with EXPO guiding principles
- Authority and stakeholder coordination and Interface management
- Technical and Financial Feasibility Study of Solar PV and other Renewable Energy systems on the Expo development covering:
- Elaboration of a financial model, including all CAPEX, OPEX, COF, ROI, payback periods, all other project related outlay costs, and any revenue that may be realized by feed-in tariff arrangements
- Review of the options for project delivery model (e.g. a DBO variant or EPC)
- Review of the best equity model
- A life-cycle comparison of different quantities of Renewable Energy assets in each of the above areas of the Expo development, reviewing energy, carbon and cost over a suitable life cycle
- A life-cycle comparison of different solar panel material
- Review of any upper limit of roof mounted solar PV assets due to excessive building structural loads
- Review of the legal environment including land use (ownership, lease) and operating license regimes for power generation assets
STAGE 2 : Concept Design:
- Site wide conceptual design for each of the selected renewable energy assets on EXPO site including their interconnectivity to distribution network and utility grid
- Coordination with building designers to ensure adequate levels of renewable energy to achieve the KPIs
- Updating of Project Design Management Plan (DMP), Project Execution Programme (PEP),Project Quality Plan (PQP)
- Undertake risk, value management and constructability reviews
- Update the Authority Approval Strategy, review and update the Procurement Strategy, submissions to Local Authorities and obtaining approvals
STAGE 3a: ER Requirements and Design Guidelines
- Provision of Employer’s Requirements for temporary and permanent Renewable Energy assets (as appropriate); EPC, FIDIC DBO, BOT, BOO or other, including suitable power production performance guarantees
- Provision of Design Guidelines for temporary and permanent Renewable Energy assets (as appropriate)
STAGE 3b: Developed Design
- Develop and refine the approved Stage 2 – Concept Design, incorporating value engineering
- Undertake risk, value engineering and constructability workshop(s),update the Authority Approval Strategy
- Review and finalize the RE Procurement Strategy
STAGE 4 : Technical Design and Tender Services
- Design all facilities required for a complete RE system in line with DBO and EPC Employer’s Requirements
- Preparation of drawings for each Stage submission as well as Tender Documents and IFC Documents
- Management of pre-qualification / shortlisting of EPC /DBO tenderers and technology suppliers
- Evaluation of tenderers’ technical offers and preparation of Tender Technical Evaluation Report
- Assistance in negotiations with the tenderers and in the award of the Construction Contract(s)
- Advisory services on the appointment of the Contractor and on the responsibilities of the contracting parties and the Engineer
- Obtaining approval of the IFC Documents for issuance to Contractor
STAGE 5a: Construction Supervision: mobilization, contract administration and site supervision services during 28 months period of construction for the Renewable Energy Works including monitoring and approving of the testing and commissioning of the Project
STAGE 5b: Sustainability Audit Services : Review the projects through design development and construction phases and confirm whether the projects are contributing to the Expo 2020 sustainability KPIs
STAGE 6 : Post Practical Completion (Defects Liability Period): Checking the operational conditions and the compliance of the Works with the requirements of the Construction Contract(s), Conducting regular visits to the Project to supervise the completion of the outstanding Works
Client
Bureau EXPO Dubai 2020Financing
Bureau EXPO Dubai 2020Period of implementation
04.2016 - 10.2021Oman - 50 MW Wind Power Plant in Dhofar
Abu Dhabi Future Energy Company - Masdar is developing a 50 MW Wind Power Plant in Dhofar Governorate in the Saltant of Oman. The project consists of 13 turbines of the state-of-art GE wind technology, 2 substations and 13km OHL. The Project design, supply, construction and commissioning was awarded to an IPC consortium. The main stakeholders of this wind farm are RAECO as the future operator, OETC as the owner of the electricity transmission line and one substation, and OPWP as the procurer of the generated electricity from this wind power plant.
intec's services
Work Package 1: Assistance in bid evaluation (EPC and O&M):
- Evaluation of technical responsiveness, of the energy yield calculations provided in the bids, the proposed project schedule, warranties, deviations, and the O&M strategy
- Provision of technical support during contract negotiations
- Assistance in the preparation of the contract documents
Work Package 2: Project management consultancy services for design review, material approval, construction management and works supervision:
- Review of the power purchase agreement (PPA) and the transmission connection agreement (TCA)
- Review and approval of design
- Witnessing of FATs for the 132 kV OHL equipment, the 132 and 33 kV switchgears, the 132/33 kV power and auxiliary transformers, the wind energy converters and associated equipment, the cabling, and the protection and SCADA systems
- Monitoring of environmental management and health and safety plans
- Construction management and works supervision, and assistance in commissioning
Client
Abu Dhabi Future Energy Company – MASDARPeriod of implementation
04.2015 - 07.2019Guinea - Analysis of Electricity Supply solutions in the region of Boke
MASDAR is developing various projects in the Caribbean and other regions of the world and sourced experts to support the engineering and project management team. These support tasks are contracted separately in the form of so-called Work Orders (WO).
The Guinea Alumina Company (GAC) currently plans to extract about 15 million tons bauxite per year and to install approximately 30 MW of power capacity. The government and other key stakeholders are keen to develop power supply solutions for both the mining sector and the civil / private sector. In light of this, the present study defines the demand and potential power supply options for mining activities and for the surrounding communities.
The overall objectives of this assignment were to:
- Prepare a demand study on the power requirements for the short, medium and long term in the regions impacted by GAC´s activities.
- Develop options, incorporating both renewable energy and existing (and new) fossil fuel based generation for meeting the determined power requirements.
intec's services
- Data collation and initial analyses (initially desktop focused)
- Site visits and meetings with key stakeholders
- Tour and inspection of available facilities
- Development of project concept and options
- Feasibility report, incorporating demand study outcomes
Client
Abu Dhabi Future Energy Company - MASDARFinancing
Abu Dhabi Future Energy Company - MASDARPeriod of implementation
10/2017 - 01/2018-
Mauritania - Construction of Solar Hybrid Systems with 16.6 MW Solar Capacity
MASDAR is developing various small and large-scale solar and wind projects in the Pacific and other regions of the world and sourced a pool of experts to support the engineering and project management team. These support tasks are contracted separately in the form of so-called Work Orders (WO). They include feasibility studies, conceptual designs, preparation of tender documents, evaluation of bids and on- and off-site project management.
Under the current work order, all together eight hybrid systems in the range up to several MW per site and with at total solar capacity of 16.6 MW (range from 1 to 3.4 MW) will be implemented under an EPC approach. Each power plant consists of solar PV, controller, and diesel generator.
intec's services
- Tasks of the "owner's representative", including coordination between the Mauritanian Electricity Company and the EPC contractor
- Design review
- Review of project execution plan
- Inspection of project construction works including QA and QC;
- Review of payment milestones
- Inspection of works' progress
- QHSE audit on all sites and submission of related report
Client
Abu Dhabi Future Energy Company PJSC - MASDARFinancing
MASDARPeriod of implementation
01.2016 - 06.2017 -
UAE - 33/11 kV Primary Substations and 22(11)/0.4 kV Distribution Substations (Lots A, B and C)
The project provides consultancy services for the establishment of power supply to medium-size development projects in Abu Dhabi. Services are divided into three lots - A, B, and C, plus a total of 4 variation orders.
- The work under Lot A covers all services required for the supply and erection of three new 33/11 kV primary substations and related cable circuits including Al-Rahba
- Lot B covers the overview of Developer's designs, bidding process and site construction works for primary and distribution substations (33/11 kV, 22(11)/0.4 kV) and 11 kV switching stations for various Developer projects such as Al Reef Villas, ICAD (M-41), South Shamka, ADNEC, Sowah Island, Saraya development, Zayed Sports City, Danet Abu Dhabi, and Building Material City.
- The services for Lot C comprise full engineering and site supervision for establishing temporary power supply to the projects identified under Lots A and B.
- Variation order 1: Additional consultancy services for 33/11 kV primary substations under Lot A
- Variation order 2: Establishment of power supply to a complex with 98 villas in Abu Dhabi (11/0.4 kV substations, 11 kV cables, feeder pillars and LV cables)
- Variation order 3: Consultancy services for the establishment of temporary and permanent power supply to the prestigious Yahsat Satellite Ground Station in Abu Dhabi involving installation, testing and commissioning of 33/11 kV primary substation, 33/11 kV package units, 11/0.4 kV substations, 33 and 11 kV cables.
- Variation order 4: Retendering of 33/11 kV primary substation at Al Rahba and inclusion of scope for extension of 11 kV feeder panels in selected 132/11 kV primary substations.
intec's services
Lot A:
- Site survey / data collection for the identification of three 33/11 kV primary substations and associated 33 kV cable routes
- Preparation of conceptual design including load flow and voltage drop analysis.
- Preparation of tender documents and conducting the entire bidding process including pre-bid clarifications, bid evaluation and preparation of contract documents.
- Review and approval of Contractors’ design documents.
- Full site supervision of Contractors’ site work including commissioning and issuance of preliminary and final acceptance certificate (PAC & FAC).
- Warranty services
Lot B:
- Review and approval of Developer’s designs for primary and distribution substations and associated cables (2 x 33/11 kV primary substations, 289 x 22/0.4 kV, 107 x 33/11 kV and 11/0.4 kV package units).
- Review and approval of tender documents prepared by the Developers for their scope of work.
- Review and approval of Developers' material submittals.
- Overview supervision of Developer’s construction work at site by way of random checks and witness of all major testing and commissioning activities.
Lot C:
- Engineering and full site supervision for establishing the temporary power supply to Developers' sites.
Variation Order 1:
- Additional consultancy services for conception design of 33/11 kV primary substations under Lot A.
Variation Order 2 (98 Villas Project):
- Conceptual study, preliminary design and detailed engineering for 11 kV distribution substation and associated cable routes.
- Preparation of tender documentation, bid evaluation and contract documents.
- Design review.
- Full site supervision and services during the warranty period.
Variation Order 3 (Yahsat Satellite Ground Station):
- Design of 33/11 kV package unit with 8.5 km 33 kV cable, one 33/11 kV primary substation and seven 11/0.4 kV distribution substations with associated 11 kV cable works.
- Preparation of conceptual and final designs for SCADA, telecommunication and telemetry systems and their testing for integration into DMS to meet Smart Grid standards.
- Overview of site supervision of the above works including supply, installation, testing, commissioning and energization.
Variation Order 4:
- Re-tendering for the 33/11 kV primary substation at Al Rahba.
- Conducting the entire bidding process for the extension of the 11 kV feeder panels.
- Full site supervision of Contractor's site works including commissioning of PAC and FAC.
- Warranty services.
Client
Abu Dhabi Distribution Company (ADDC)Financing
Abu Dhabi Distribution Company (ADDC)Period of implementation
01.2008 - 01.2015 -
UAE - Construction Management of Substation and Chiller Works at Yas Island
The installation of new chillers in the residential areas of Yas Island led to an increase of load demand which required the construction of a new 22/0.4 kV distribution substation and the transfer of LV load between different feeder pillars.
In addition, the project covers the installation of an energy-efficient solar-powered street lighting system in the project area.
intec's services
- Review of Subcontractor's technical and material submittals;
- Supervision of Subcontractor's site construction activities;
- Coordination between Subcontractor, the Client's Consultant and the Client RAPM;
- Ensure the completion of works in line with ADDC's specifications;
- Variation order: Coordination and site supervision for the installation of a street-lighting system.
Client
Royal Architect Project Management LLC (RAPM)Financing
Royal Architect Project Management LLC (RAPM)Period of implementation
05.2013 - 01.2014
Mauritania - Construction of Solar Hybrid Systems with 16.6 MW Solar Capacity
MASDAR is developing various small and large-scale solar and wind projects in the Pacific and other regions of the world and sourced a pool of experts to support the engineering and project management team. These support tasks are contracted separately in the form of so-called Work Orders (WO). They include feasibility studies, conceptual designs, preparation of tender documents, evaluation of bids and on- and off-site project management.
Under the current work order, all together eight hybrid systems in the range up to several MW per site and with at total solar capacity of 16.6 MW (range from 1 to 3.4 MW) will be implemented under an EPC approach. Each power plant consists of solar PV, controller, and diesel generator.
intec's services
- Tasks of the "owner's representative", including coordination between the Mauritanian Electricity Company and the EPC contractor
- Design review
- Review of project execution plan
- Inspection of project construction works including QA and QC;
- Review of payment milestones
- Inspection of works' progress
- QHSE audit on all sites and submission of related report
Client
Abu Dhabi Future Energy Company PJSC - MASDARFinancing
MASDARPeriod of implementation
01.2016 - 06.2017UAE - 33/11 kV Primary Substations and 22(11)/0.4 kV Distribution Substations (Lots A, B and C)
The project provides consultancy services for the establishment of power supply to medium-size development projects in Abu Dhabi. Services are divided into three lots - A, B, and C, plus a total of 4 variation orders.
- The work under Lot A covers all services required for the supply and erection of three new 33/11 kV primary substations and related cable circuits including Al-Rahba
- Lot B covers the overview of Developer's designs, bidding process and site construction works for primary and distribution substations (33/11 kV, 22(11)/0.4 kV) and 11 kV switching stations for various Developer projects such as Al Reef Villas, ICAD (M-41), South Shamka, ADNEC, Sowah Island, Saraya development, Zayed Sports City, Danet Abu Dhabi, and Building Material City.
- The services for Lot C comprise full engineering and site supervision for establishing temporary power supply to the projects identified under Lots A and B.
- Variation order 1: Additional consultancy services for 33/11 kV primary substations under Lot A
- Variation order 2: Establishment of power supply to a complex with 98 villas in Abu Dhabi (11/0.4 kV substations, 11 kV cables, feeder pillars and LV cables)
- Variation order 3: Consultancy services for the establishment of temporary and permanent power supply to the prestigious Yahsat Satellite Ground Station in Abu Dhabi involving installation, testing and commissioning of 33/11 kV primary substation, 33/11 kV package units, 11/0.4 kV substations, 33 and 11 kV cables.
- Variation order 4: Retendering of 33/11 kV primary substation at Al Rahba and inclusion of scope for extension of 11 kV feeder panels in selected 132/11 kV primary substations.
intec's services
Lot A:
- Site survey / data collection for the identification of three 33/11 kV primary substations and associated 33 kV cable routes
- Preparation of conceptual design including load flow and voltage drop analysis.
- Preparation of tender documents and conducting the entire bidding process including pre-bid clarifications, bid evaluation and preparation of contract documents.
- Review and approval of Contractors’ design documents.
- Full site supervision of Contractors’ site work including commissioning and issuance of preliminary and final acceptance certificate (PAC & FAC).
- Warranty services
Lot B:
- Review and approval of Developer’s designs for primary and distribution substations and associated cables (2 x 33/11 kV primary substations, 289 x 22/0.4 kV, 107 x 33/11 kV and 11/0.4 kV package units).
- Review and approval of tender documents prepared by the Developers for their scope of work.
- Review and approval of Developers' material submittals.
- Overview supervision of Developer’s construction work at site by way of random checks and witness of all major testing and commissioning activities.
Lot C:
- Engineering and full site supervision for establishing the temporary power supply to Developers' sites.
Variation Order 1:
- Additional consultancy services for conception design of 33/11 kV primary substations under Lot A.
Variation Order 2 (98 Villas Project):
- Conceptual study, preliminary design and detailed engineering for 11 kV distribution substation and associated cable routes.
- Preparation of tender documentation, bid evaluation and contract documents.
- Design review.
- Full site supervision and services during the warranty period.
Variation Order 3 (Yahsat Satellite Ground Station):
- Design of 33/11 kV package unit with 8.5 km 33 kV cable, one 33/11 kV primary substation and seven 11/0.4 kV distribution substations with associated 11 kV cable works.
- Preparation of conceptual and final designs for SCADA, telecommunication and telemetry systems and their testing for integration into DMS to meet Smart Grid standards.
- Overview of site supervision of the above works including supply, installation, testing, commissioning and energization.
Variation Order 4:
- Re-tendering for the 33/11 kV primary substation at Al Rahba.
- Conducting the entire bidding process for the extension of the 11 kV feeder panels.
- Full site supervision of Contractor's site works including commissioning of PAC and FAC.
- Warranty services.
Client
Abu Dhabi Distribution Company (ADDC)Financing
Abu Dhabi Distribution Company (ADDC)Period of implementation
01.2008 - 01.2015UAE - Construction Management of Substation and Chiller Works at Yas Island
The installation of new chillers in the residential areas of Yas Island led to an increase of load demand which required the construction of a new 22/0.4 kV distribution substation and the transfer of LV load between different feeder pillars.
In addition, the project covers the installation of an energy-efficient solar-powered street lighting system in the project area.
intec's services
- Review of Subcontractor's technical and material submittals;
- Supervision of Subcontractor's site construction activities;
- Coordination between Subcontractor, the Client's Consultant and the Client RAPM;
- Ensure the completion of works in line with ADDC's specifications;
- Variation order: Coordination and site supervision for the installation of a street-lighting system.
Client
Royal Architect Project Management LLC (RAPM)Financing
Royal Architect Project Management LLC (RAPM)Period of implementation
05.2013 - 01.2014-
UAE - 400 kV Switching Station at Hameem Junction / Mussafah
The works for the new 400 kV switching station at Hameem Junction were divided into two lots which had the following technical features:
Lot 1: Substation Works, including:
- 400 kV gas-insulated (GIS) switchgear with a double busbar system,
- 6 OHL bays, 2 bus section bays, 2 bus coupler bays, 2 spare OHL bays, 2 spare inter-bus transformer bays, space for two spare feeders,
- power and control cables, control and protection, coordination with the remote ends, interface with the load dispatch centre’s SCADA system, and communication works,
- fire-fighting systems, air conditioning, and civil works.
Lot 2: 200 kV Overhead Line Works, including:
- Loop-in and loop-out of the 400 kV d.c. lines from Madinat Zayed, Mussafah, AASW/Taweelah B,
- Line route survey, soil investigations, and access roads,
- Design, supply and installation of foundations,
- Design, supply, erection and painting of towers and gantries
- Supply and installation of insulators, conductors, and OPGW,
- Installation of an aircraft warning system.
intec's services
- Data collection and site survey,
- Preparation of preliminary and final design,
- Elaboration of costs and budget,
- Preparation of tender documents and evaluation of bids,
- Site supervision during the construction period,
- Testing,
- Site supervision during the warranty period.
Client
Abu Dhabi Transmission and Despatch Company (TRANSCO)Financing
TRANSCOPeriod of implementation
05.2008 - 12.2012 -
UAE - Establishment of Power Supply to Yas Island
In order to sustain the development of different regions of Abu Dhabi Island, ADDC, in collaboration with private developers, initiated several projects to expand the electrical network by adding primary substations and integrating them into the existing power network. Among other projects, the private developer ALDAR Properties PJSC embarked on the development of Yas Island to develop it into a major touristic, residential and commercial city located in the suburbs of Abu Dhabi Island.
Accordingly, a project was initiated to provide consulting services for the network expansion projects, both for temporary and permanent power supply, with the aim to assure the compliance of the installations with ADDC's / ADWEA's design guidelines, specifications and the overall project schedule.
intec's services
Stage 1:
- Review and approval of the Developer's 33 kV design
- Identification of 33 kV cable routes including their coordination with the town planning department
- Review and approval of Developer's tender documents and bid evaluation/recommendations
- Review and approval of material submitted by the Developer
- Review of progress reporting
Stage 2:
- As above, but for the 22 kV and the LV level.
Stage 3:
- Field supervision (overview) of construction works at the Developer's site
- Inspection of site works to ensure compliance with ADDC's requirements
- Verification of quantities and related documents / drawings to be handed over to ADDC
- Review of progress reporting.
Client
Abu Dhabi Distribution Company (ADDC)Financing
Abu Dhabi Distribution Company (ADDC)Period of implementation
02.2008 - 06.2012 -
UAE - 11 kV Feeder Panels in some 132/11 kV Primary Substations in Abu Dhabi Island
22 (twenty two) 132/11 kV primary substations exist in Abu Dhabi Island. In line with ADDC's standards, the number of 11 kV outgoing feeder panels per substation is 48 (forty eight). This standard design was adopted from the year 2005. However, most of the primaries commissioned prior to 2005 have less than 48 (forty eight) 11 kV outgoing feeders.
With the objective to install additional 11 kV outgoing feeder panels, ADWEA commissioned a study on 12 selected existing 132/11 kV primary substations in Abu Dhabi Island and the implementation of the recommendations for network augmentation at these substations.
The scope of these consultancy services included study, design, preparation of tender documents, tendering and supervision of the supply, the installation and the commissioning of 11 kV outgoing feeder panels at some of the above primary substations. The aim was to utilize the available spare FIRM capacity to serve new customers / connections, to reinforce the existing network and also provide panels for connecting the battery energy storage system (BESS).
intec's services
- Site survey for 12 (twelve) 132/11 kV primary substations;
- Submission of site survey report to ADWEA for approval;
- Submission of scope of work (SoW) and bills of quantities (BoQ) to ADWEA for approval;
Client
Abu Dhabi Water & Electricity Authority (ADWEA)Financing
Abu Dhabi Water & Electricity Authority (ADWEA)Period of implementation
06.2009 - 11.2010
UAE - 400 kV Switching Station at Hameem Junction / Mussafah
The works for the new 400 kV switching station at Hameem Junction were divided into two lots which had the following technical features:
Lot 1: Substation Works, including:
- 400 kV gas-insulated (GIS) switchgear with a double busbar system,
- 6 OHL bays, 2 bus section bays, 2 bus coupler bays, 2 spare OHL bays, 2 spare inter-bus transformer bays, space for two spare feeders,
- power and control cables, control and protection, coordination with the remote ends, interface with the load dispatch centre’s SCADA system, and communication works,
- fire-fighting systems, air conditioning, and civil works.
Lot 2: 200 kV Overhead Line Works, including:
- Loop-in and loop-out of the 400 kV d.c. lines from Madinat Zayed, Mussafah, AASW/Taweelah B,
- Line route survey, soil investigations, and access roads,
- Design, supply and installation of foundations,
- Design, supply, erection and painting of towers and gantries
- Supply and installation of insulators, conductors, and OPGW,
- Installation of an aircraft warning system.
intec's services
- Data collection and site survey,
- Preparation of preliminary and final design,
- Elaboration of costs and budget,
- Preparation of tender documents and evaluation of bids,
- Site supervision during the construction period,
- Testing,
- Site supervision during the warranty period.
Client
Abu Dhabi Transmission and Despatch Company (TRANSCO)Financing
TRANSCOPeriod of implementation
05.2008 - 12.2012UAE - Establishment of Power Supply to Yas Island
In order to sustain the development of different regions of Abu Dhabi Island, ADDC, in collaboration with private developers, initiated several projects to expand the electrical network by adding primary substations and integrating them into the existing power network. Among other projects, the private developer ALDAR Properties PJSC embarked on the development of Yas Island to develop it into a major touristic, residential and commercial city located in the suburbs of Abu Dhabi Island.
Accordingly, a project was initiated to provide consulting services for the network expansion projects, both for temporary and permanent power supply, with the aim to assure the compliance of the installations with ADDC's / ADWEA's design guidelines, specifications and the overall project schedule.
intec's services
Stage 1:
- Review and approval of the Developer's 33 kV design
- Identification of 33 kV cable routes including their coordination with the town planning department
- Review and approval of Developer's tender documents and bid evaluation/recommendations
- Review and approval of material submitted by the Developer
- Review of progress reporting
Stage 2:
- As above, but for the 22 kV and the LV level.
Stage 3:
- Field supervision (overview) of construction works at the Developer's site
- Inspection of site works to ensure compliance with ADDC's requirements
- Verification of quantities and related documents / drawings to be handed over to ADDC
- Review of progress reporting.
Client
Abu Dhabi Distribution Company (ADDC)Financing
Abu Dhabi Distribution Company (ADDC)Period of implementation
02.2008 - 06.2012UAE - 11 kV Feeder Panels in some 132/11 kV Primary Substations in Abu Dhabi Island
22 (twenty two) 132/11 kV primary substations exist in Abu Dhabi Island. In line with ADDC's standards, the number of 11 kV outgoing feeder panels per substation is 48 (forty eight). This standard design was adopted from the year 2005. However, most of the primaries commissioned prior to 2005 have less than 48 (forty eight) 11 kV outgoing feeders.
With the objective to install additional 11 kV outgoing feeder panels, ADWEA commissioned a study on 12 selected existing 132/11 kV primary substations in Abu Dhabi Island and the implementation of the recommendations for network augmentation at these substations.
The scope of these consultancy services included study, design, preparation of tender documents, tendering and supervision of the supply, the installation and the commissioning of 11 kV outgoing feeder panels at some of the above primary substations. The aim was to utilize the available spare FIRM capacity to serve new customers / connections, to reinforce the existing network and also provide panels for connecting the battery energy storage system (BESS).
intec's services
- Site survey for 12 (twelve) 132/11 kV primary substations;
- Submission of site survey report to ADWEA for approval;
- Submission of scope of work (SoW) and bills of quantities (BoQ) to ADWEA for approval;