Environment - Project examples
-
Bangladesh - Energy Efficiency in Grid Based Power Supply Project (EEGBPSP)
The P.R. of Bangladesh received a loan from KfW Development Bank for the "Energy Efficiency in Grid Based Power Supply Project". Objective of this project is to increase reliability and efficiency of the electricity supply in the country through expanding and improving the 230 and 132 kV power transmission systems of PGCB. Technical measures under the project include the following:
- new construction, extension or rehabilitation of 230/132 kV, 2 x 225/300 MVA GIS and AIS substations,
- new construction of 132/33 kV GIS and AIS substations,
- new construction, renovation or stringing of second circuit of 230 kV and 132 kV transmission lines (single or double-circuit), including OPGW,
- various line in/line out connections to 132 and 230 kV substations,
- installation of additional line bays at some 132 or 230 kV substations,
divided into 7 lots.
intec's services
- Contract management, administration and coordination with Employer and Contractors;
- Preparation of tender documents and assistance during the tender process;
- Design review, participation in FAT and acceptance testing;
- Progress monitoring of Contractors' site works;
- Environmental and social management monitoring, gap-closing;
- Participation and support in site testing, commissioning and handing over;
- Support during the Defects Liability Period;
- Training;
- Support in reporting to the Bank.
Client
Power Grid Company of Bangladesh Ltd. - PGCBFinancing
Kreditanstalt für Wiederaufbau (KfW)Period of implementation
5.3.2018 - 4.7.2022 -
Gambia - Environmental services for Solar PV development
The Republic of Gambia, through the National Water and Electricity Company Limited- NAWEC (the Client), is seeking the development of Solar PV power generation in the country. The objective of the assignment is to assess the technical viability of constructing solar PV power generation in Gambia. The study includes three models: EPC 20 MW at Jambur, IPP 120 - 130 MW at Soma and separate Battery Energy Storage Systems (grid connected) at Brikama. Furthermore, bidding documents are prepared for the grid connected PV + BESS at Jambur, including grid connection based on WB's standard procurement documents.
intec's services
A range of environmental services were carried out by intec, including the following:
- Project inception and implementation planning
- Solar Resource Assessment, Solar Data and Meteorological Conditions
- Site selection and studies for grid connected photovoltaic and battery energy storage (PV + BESS)
- Options for integration into existing power system
- Analysis of global environmental benefits and performance of legal due diligence
- Preliminary analysis of environmental and social impacts
- Training and capacity strengthening program
- The study emphasises on the carbon gains (avoided carbon emissions) from electricity generation by solar PV from different generation models. For each of them, identification and assessment of relevant environmental and social impacts was carried out in view of identifying the most sustainable option.
(The above services were provided in the framework of the project Feasibility Study for Solar PV Development - Jambur, EPC 20 MW and Soma, IPP 120 - 130 MW)
Client
National Water and Electricity Company Limited (NA-WEC)Financing
World Bank (WB)Period of implementation
02.2018 – 04/2020 -
Serbia - EHS services for the Čibuk 1 Wind Farm Project
Vetroelecktrane is developing and executing, together with their major shareholders Abu Dhabi Future Energy Company-Masdar and Continental Wind Partners (CWP), a wind farm consisting of 57 Wind Turbine Generators (WTGs) of 110m hub height and 2.8 MW rated power, main transformer station and corresponding infrastructure. The consultant has been appointed by the client to manage the project as owner's engineer, providing Project Management Consulting Services (PMC) and site supervision services (including design review, procurement, supervision of construction, commissioning, start-up and testing) as well as technical advice and support during negotiations with third parties.
intec's services
The EHS activities relevant to the project comprise the following:
Provide assistance to the client with any local authorities or other stakeholders.
Performance of all health and safety activities prescribed by the Serbian law
Provide assistance with maintaining compliance with EBRD and IFC requirements
Supervision of all activities in relation to the connection to the utility network and services performed in relation to the Environmental Management Plan
- Technical and legal assistance during contracts' execution (review of design documentation and its compliance with the ESAP, supervision of contractors' works, assistance in project management, assistance during defect notification period)
- Monitor the mitigation measures undertaken by the Contractor or other third parties during the construction and commissioning phases and review and provide comments on all environmental reports
- Assistance in the implementation of the ESAP/ESMPP
- Performance of inspection, site supervision, health & safety, environmental activities
The above activities were carried out in the framework of the Čibuk 1 Wind Farm Project.
Client
Vetroelecktrane Balcana (VEBG) D.O.OFinancing
Vetroelecktrane Balcana (VEBG) D.O.OPeriod of implementation
03.2017 - 01.2019
Bangladesh - Energy Efficiency in Grid Based Power Supply Project (EEGBPSP)
The P.R. of Bangladesh received a loan from KfW Development Bank for the "Energy Efficiency in Grid Based Power Supply Project". Objective of this project is to increase reliability and efficiency of the electricity supply in the country through expanding and improving the 230 and 132 kV power transmission systems of PGCB. Technical measures under the project include the following:
- new construction, extension or rehabilitation of 230/132 kV, 2 x 225/300 MVA GIS and AIS substations,
- new construction of 132/33 kV GIS and AIS substations,
- new construction, renovation or stringing of second circuit of 230 kV and 132 kV transmission lines (single or double-circuit), including OPGW,
- various line in/line out connections to 132 and 230 kV substations,
- installation of additional line bays at some 132 or 230 kV substations,
divided into 7 lots.
intec's services
- Contract management, administration and coordination with Employer and Contractors;
- Preparation of tender documents and assistance during the tender process;
- Design review, participation in FAT and acceptance testing;
- Progress monitoring of Contractors' site works;
- Environmental and social management monitoring, gap-closing;
- Participation and support in site testing, commissioning and handing over;
- Support during the Defects Liability Period;
- Training;
- Support in reporting to the Bank.
Client
Power Grid Company of Bangladesh Ltd. - PGCBFinancing
Kreditanstalt für Wiederaufbau (KfW)Period of implementation
5.3.2018 - 4.7.2022Gambia - Environmental services for Solar PV development
The Republic of Gambia, through the National Water and Electricity Company Limited- NAWEC (the Client), is seeking the development of Solar PV power generation in the country. The objective of the assignment is to assess the technical viability of constructing solar PV power generation in Gambia. The study includes three models: EPC 20 MW at Jambur, IPP 120 - 130 MW at Soma and separate Battery Energy Storage Systems (grid connected) at Brikama. Furthermore, bidding documents are prepared for the grid connected PV + BESS at Jambur, including grid connection based on WB's standard procurement documents.
intec's services
A range of environmental services were carried out by intec, including the following:
- Project inception and implementation planning
- Solar Resource Assessment, Solar Data and Meteorological Conditions
- Site selection and studies for grid connected photovoltaic and battery energy storage (PV + BESS)
- Options for integration into existing power system
- Analysis of global environmental benefits and performance of legal due diligence
- Preliminary analysis of environmental and social impacts
- Training and capacity strengthening program
- The study emphasises on the carbon gains (avoided carbon emissions) from electricity generation by solar PV from different generation models. For each of them, identification and assessment of relevant environmental and social impacts was carried out in view of identifying the most sustainable option.
(The above services were provided in the framework of the project Feasibility Study for Solar PV Development - Jambur, EPC 20 MW and Soma, IPP 120 - 130 MW)
Client
National Water and Electricity Company Limited (NA-WEC)Financing
World Bank (WB)Period of implementation
02.2018 – 04/2020Serbia - EHS services for the Čibuk 1 Wind Farm Project
Vetroelecktrane is developing and executing, together with their major shareholders Abu Dhabi Future Energy Company-Masdar and Continental Wind Partners (CWP), a wind farm consisting of 57 Wind Turbine Generators (WTGs) of 110m hub height and 2.8 MW rated power, main transformer station and corresponding infrastructure. The consultant has been appointed by the client to manage the project as owner's engineer, providing Project Management Consulting Services (PMC) and site supervision services (including design review, procurement, supervision of construction, commissioning, start-up and testing) as well as technical advice and support during negotiations with third parties.
intec's services
The EHS activities relevant to the project comprise the following:
Provide assistance to the client with any local authorities or other stakeholders.
Performance of all health and safety activities prescribed by the Serbian law
Provide assistance with maintaining compliance with EBRD and IFC requirements
Supervision of all activities in relation to the connection to the utility network and services performed in relation to the Environmental Management Plan
- Technical and legal assistance during contracts' execution (review of design documentation and its compliance with the ESAP, supervision of contractors' works, assistance in project management, assistance during defect notification period)
- Monitor the mitigation measures undertaken by the Contractor or other third parties during the construction and commissioning phases and review and provide comments on all environmental reports
- Assistance in the implementation of the ESAP/ESMPP
- Performance of inspection, site supervision, health & safety, environmental activities
The above activities were carried out in the framework of the Čibuk 1 Wind Farm Project.
Client
Vetroelecktrane Balcana (VEBG) D.O.OFinancing
Vetroelecktrane Balcana (VEBG) D.O.OPeriod of implementation
03.2017 - 01.2019-
Uganda - 10 MW PV Solar Project in Tororo District
The Netherlands Development Finance Company (FMO) invests into a 10 MW PV solar power project to be developed, owned and operated by the company Tororo Solar North Ltd. (TSN). FMO contracted the services of a consultant to carry out lenders' technical, environmental and social due diligence of the project, construction supervision and monitoring of operational performance.
intec's services
A. Due Diligence Phase
- Project site assessment: topography, solar resource and ambient conditions; logistics; etc.
- Review of technology and plant design
- Review of energy yield analysis and forecasts for expected power production in kWh
- Review of project contracts / agreements (i.a. PPA, interconnection, O&M, water supply & land agreements)
- Review of construction and completion testing, of off-take structure (PPA) and of O&M structure
- Electrical interconnection review
- Check and follow-up of permits and licenses
- Review of expected project costs and of financial model assumptions
- Review of the project's environmental and social impact assessment (ESIA) process and report
- Summary of recommendations and proposed actions in a draft environmental and social action plan (ESAP)
B. Construction and Commissioning Phase
- Construction monitoring and quality assurance
- Design review and approval
- Review of acceptance testing procedures and test witnessing
- Participation in commissioning and taking-over
C. Operational Phase (services on call until 2032)
Monitoring of punch list items, review of operational performance, periodical review of operation reports
Client
Netherlands Development Finance Company ("FMO")Financing
Access Uganda Solar LimitedPeriod of implementation
20.3.2015 - 31.7.2018 -
Zambia - ESIA and strengthening of environmental capacity
Kafue Gorge Regional Training Centre (KGRTC), established in 1989, provides quality training to regional power utilities. KGRTC intended to develop a small hydropower station at Kafue Gorge with ancillary transmission structures, termination and connection to the grid. The station has been constructed between the existing Kafue Gorge Power Station dam site and the tailrace of the Kafue Gorge Lower Hydropower Station, the size of the SHPP shall be a result of the present feasibility study. The feasibility study led to the preparation of a full basic design and of tender documents for the procurement of an EPC contractor.
intec's services
The following services were provided:
Review of existing pre-feasibility studies and related reports
Selection and assessment of project alternatives and options
Environmental and Social Impact Assessment (ESIA)
- collect baseline data of physical, biological and socio-cultural environment of project affected areas
- assess impacts of major significance and develop mitigation and management programs to prevent, minimize or offset the adverse impacts
Elaboration E&S risk and mitigation list
ESIA scoping study
Training needs assessment, elaboration of training programme and schedule, conduction of training courses
Strengthening of the capacity of KGRTC to design, maintain and implement the ESMS for SHPP construction and operation
(The above activities were carried out in the framework of the project Feasibility Study for KGRTC Small Hydropower Station)
Client
Kafue Gorge Regional Training Centre (KGRTC)Financing
Swedish International Development Cooperation AgencyPeriod of implementation
22.6.2015 - 31.10.2017
Uganda - 10 MW PV Solar Project in Tororo District
The Netherlands Development Finance Company (FMO) invests into a 10 MW PV solar power project to be developed, owned and operated by the company Tororo Solar North Ltd. (TSN). FMO contracted the services of a consultant to carry out lenders' technical, environmental and social due diligence of the project, construction supervision and monitoring of operational performance.
intec's services
A. Due Diligence Phase
- Project site assessment: topography, solar resource and ambient conditions; logistics; etc.
- Review of technology and plant design
- Review of energy yield analysis and forecasts for expected power production in kWh
- Review of project contracts / agreements (i.a. PPA, interconnection, O&M, water supply & land agreements)
- Review of construction and completion testing, of off-take structure (PPA) and of O&M structure
- Electrical interconnection review
- Check and follow-up of permits and licenses
- Review of expected project costs and of financial model assumptions
- Review of the project's environmental and social impact assessment (ESIA) process and report
- Summary of recommendations and proposed actions in a draft environmental and social action plan (ESAP)
B. Construction and Commissioning Phase
- Construction monitoring and quality assurance
- Design review and approval
- Review of acceptance testing procedures and test witnessing
- Participation in commissioning and taking-over
C. Operational Phase (services on call until 2032)
Monitoring of punch list items, review of operational performance, periodical review of operation reports
Client
Netherlands Development Finance Company ("FMO")Financing
Access Uganda Solar LimitedPeriod of implementation
20.3.2015 - 31.7.2018Zambia - ESIA and strengthening of environmental capacity
Kafue Gorge Regional Training Centre (KGRTC), established in 1989, provides quality training to regional power utilities. KGRTC intended to develop a small hydropower station at Kafue Gorge with ancillary transmission structures, termination and connection to the grid. The station has been constructed between the existing Kafue Gorge Power Station dam site and the tailrace of the Kafue Gorge Lower Hydropower Station, the size of the SHPP shall be a result of the present feasibility study. The feasibility study led to the preparation of a full basic design and of tender documents for the procurement of an EPC contractor.
intec's services
The following services were provided:
Review of existing pre-feasibility studies and related reports
Selection and assessment of project alternatives and options
Environmental and Social Impact Assessment (ESIA)
- collect baseline data of physical, biological and socio-cultural environment of project affected areas
- assess impacts of major significance and develop mitigation and management programs to prevent, minimize or offset the adverse impacts
Elaboration E&S risk and mitigation list
ESIA scoping study
Training needs assessment, elaboration of training programme and schedule, conduction of training courses
Strengthening of the capacity of KGRTC to design, maintain and implement the ESMS for SHPP construction and operation
(The above activities were carried out in the framework of the project Feasibility Study for KGRTC Small Hydropower Station)